Bangalore property|2bhk apartments for sale in bangalore|flats|lands for sale in Bangalore
Anekal
Bannerghatta Road
Devanahalli Road
Electronic City
Hosur Road
Indira Nagar
Kanakapura Road
Koramangala
Sarjapur Road
Vijayanagar
Whitefield
Before
getting of the flats purchased by someone, getting Occupancy Certificate (OC)
may be a “must have document”. If you're denied of identical, then the patron
court will return to your rescue.
The Bandra
shopper Disputes Redressal Forum noting that the Occupancy Certificate is an
important demand for a flat-buyer has ordered Dharia Developers to administer
the buyer, the Occupancy Certificate inside a specific time.
As per
an agreement dated september 26, 2006, Mr. Mehul Thakkar bought 2
flats on the sixth floor (601 and 602) of an dwelling by paying Rs forty.25lakh
for every of the flats, the remaining 1lakh per flat was in agreement to be
paid at the time of delivery of possession. It seems that M/s. Dharia
Developers had secured to administer the possession of the flats inside twelve
months from the date of agreement. However, Thakkar is nevertheless to get the
Occupancy Certificate or the Completion Certificate for these flats. Hence,
Thakkar sent a notice to the builder hard to please identical. Once the builder
did not respond, Thakkar filed a grievance before the Forum and additionally an
application seeking interim relief.
In their
defense, Dharia Developers argued that Thakkar wished to merge each the flats
into one unit, as per his letter in september 2006. The builder claimed that
tho' this was against the building's approved set up, they allowable Thakkar to
do thus at his own expense when obtaining an approval from the enabling authorities.
The builder expressed that since Thakkar could not complete the add time, the
Occupancy Certificate could not be obtained from the authorities. Hence,
they're not chargeable for the delay in returning the possession and also the
Occupancy Certificate to Thakkar.
In their
interim order, that is common for each of Thakkar's flats, the Bandra shopper
Disputes Redressal Forum has command the builder as having committed deficiency
of service. The forum discovered, “These explanations are hardly
satisfactory, as a result of it had been an obligation incurred by Thakkar. If
Thakkar had not allotted the modifications that he had instructed, the builder
might have completed the development no matter Thakkar's suggestions.” The
forum noted that tho' Thakkar had given the letter informing of the
modifications to the builder in september 2006, the flat's construction is
incomplete even when 3 years. “The builder ought to have completed the
constructions, internal furthermore as external, as per the initial set up,
since the modifications were at Thakkar's instance. The builder wasn't needed
to attend until the modifications were completed. This shows that the builder
has imply a lame excuse for not finishing the development and for not getting
the Occupancy Certificate.
The builder
received nearly the complete thought of the flat, over Rs 40lakh in 2006. He
has preserved the number and used identical, however has not collected the
Occupancy Certificate.” The Forum additionally command, “Obtaining OC is an
important demand below the MOFA(Maharashtra possession Flat Act) and also the
flat purchased can't be wrongfully occupied, unless the Occupancy Certificate
is obtained by the builder. The builder has not created one piece of paper to
point out that he has taken effective steps with the competent authority for
getting Occupancy Certificate.”
More,
Bangalore real estateAnekal
Bannerghatta Road
Devanahalli Road
Electronic City
Hosur Road
Indira Nagar
Kanakapura Road
Koramangala
Sarjapur Road
Vijayanagar
Whitefield
No comments:
Post a Comment